Option cost
The New Rules of Measurement (NRM) are published by the Royal Institute of Chartered Surveyors (RICS). They provide a standard set of measurement rules for estimating, cost planning, procurement and whole-life costing for construction projects.
According to NRM1: Order of cost estimating and cost planning for capital building work, an option cost is:
'...an estimate of the cost of alternative design solutions to achieve the employer’s objectives; so that they can be compared and appraised. Option costs will be incorporated in the overarching cost report.'
NRM1 suggests it may be necessary to estimate the cost of alternative development scenarios for a site as part of RIBA Work Stages A and B or Gateways 1 and 2.
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.
Government approach could undermine delivery and regeneration.